Projects

CDOT Kettle Creek Poly

March 18, 2016

Maintenance on the deck of the bridge that carries Voyager Parkway over Kettle Creek. Work was performed at night. Single lane closures in both the northbound and southbound directions. Removed existing overlay on the concrete deck. Installed new deck joints, performed concrete patching, installed a new overlay on the bridge deck.