Projects

Weaverville Poly

February 24, 2021 Myers and Sons Construction won this contract through Caltrans as a prime contractor. It was won at $7.7 million with 230 working days. The scope of the work includes bridge deck repair, preparing and placing polyester concrete overlay, and rail replacements on nine bridges in Siskiyou & Trinity counties.