Projects

Dollar Pump Station

March 18, 2015

The North Tahoe Public Utility District selected Myers as the prime contractor to complete this project. Project scope of work included the replacement of four 160HP pumps, replacement over 90% of electrical equipment infrastructure and upgrades to the existing standby generator system. This contract also included heavy civil site improvements, structural upgrades to the control building and retaining wall upgrades.