Ukiah Bridge Repair
July 19, 2018Categories
Road and Bridge RestorationMyers and Sons Construction won this conctract through Caltrans as a prime contractor. It was won at a bid price of $741,498 with 95 working days. The scope of work included placing 26 cubic yards of polyester concrete overlay and 67,000 square-feet of methacrylate over various bridges in and around Ukiah, CA.